- #01Asbestos / lead paint assessment (commercial)Life Safety
Commercial demolition triggers NESHAP asbestos survey and RRP lead paint compliance for applicable structures.
40 CFR 61 Subpart M40 CFR 745 - #02Environmental and hazardous materialsLife Safety
Commercial structures may contain additional hazmat (mercury switches, PCB ballasts, refrigerants) requiring special handling.
FDEP hazmat rules40 CFR - #03Structural protection and sequencingLife Safety
Demolition sequencing must preserve stability of remaining/adjacent structures.
FBC-EB 1401
Commercial Demolition
Demolition of an existing commercial building
Last updated: Apr 20, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Sealed Demolition PlansDemolition plans sealed by a Florida-registered design professional
- Site Plan / SurveySite plan or survey showing structures to be demolished and surrounding features
Conditional
- Asbestos SurveyAsbestos survey guidance based on year built and risk; verify requirement during downstream review as needed.WhenGuidance only (non-blocking at intake): may be required depending on year built and asbestos risk factors.
- Environmental AssessmentEnvironmental assessment for hazardous materials, lead paint, and other contaminantsWhenRequired for commercial structures where hazardous materials may be present
Section 2
Plan Review Criteria
What FCC's plans examiner looks for on this project type, by trade. Items are grouped by priority — life-safety first. Building department checks may go further; this is the FCC private provider scope under FL Statute 553.791.
BuildingRequired
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Building
Final Building
RequiredTypical Final- Structure fully demolishedCritical
Verify permitted structure is completely demolished and removed from site
FBC-B 110.3 - Utility disconnectionCritical
Verify all utilities (electric, gas, water, sewer) are properly disconnected and capped
FBC-B 3303.5 - Site conditionCritical
Verify site is graded, debris is removed, and no hazardous materials remain
FBC-B 3303.3 - Erosion control
Verify erosion control measures are in place if required
FBC-B 3303.2