- #01Fire-rated unit separationLife Safety
Dwelling-unit and corridor separations must maintain the original fire-resistance rating through any new work.
FBC-B 420FBC-B 711FBC-B 708 - #02Means of egress in altered areasLife Safety
Alterations must not reduce the capacity, width, or arrangement of existing means of egress.
FBC-B 1004FBC-B 1005 - #03Structural alterations (MF)Life Safety
Wall removal or beam substitution requires engineered detail.
FBC-B 1603FBC-EB Ch. 4 - #04Sound transmission (altered party walls)Performance
Altered inter-unit assemblies must meet FBC-B 1206 STC/IIC minimums.
FBC-B 1206
Multi Family Alteration
Includes remodeling of existing condos or apartments where structural, mechanical, electrical, and/or plumbing changes are being made
Last updated: Apr 20, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Scope of Work DescriptionVery detailed written scope of work describing all work to be performed
- Construction Plans Sealed by a Florida Registered Design ProfessionalConstruction plans sealed by a Florida-registered design professional reflecting the full scope of alteration work.
Conditional
- Product ApprovalsFlorida Product Approvals for any regulated components being installedWhenRequired if installing new windows, doors, roofing, or other regulated products
Section 2
Plan Review Criteria
What FCC's plans examiner looks for on this project type, by trade. Items are grouped by priority — life-safety first. Building department checks may go further; this is the FCC private provider scope under FL Statute 553.791.
BuildingRequired
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Building
Rough Framing
Conditional- Wall stud spacing and sizeCritical
Verify stud size and spacing match approved plans
FBC-R R602.3FBC-R R602.3.1 - Headers and beamsCritical
Verify header and beam sizes over openings per plans
FBC-R R602.7 - Top and bottom plate connectionsCritical
Verify double top plates with proper lapping and anchored bottom plates
FBC-R R602.3.2 - Corner and intersection bracingCritical
Verify proper bracing at corners and wall intersections
FBC-R R602.10 - Window and door rough openingsCritical
Verify rough openings match approved plans for size and location
FBC-R R602.7 - Hurricane straps and hold-downsCritical
Verify hurricane straps and hold-down hardware installed per plans
FBC-R R802.11 - Fire blocking
Verify fire blocking is installed at required locations
FBC-R R602.8
Roof Dry In, In Progress
Conditional- Underlayment installationCritical
Verify roof underlayment is installed per code and manufacturer specs
FBC-R R905.1.1 - Drip edge installationCritical
Verify drip edge is installed at eaves and rakes
FBC-R R905.2.8.5 - Valley and flashingCritical
Verify valley flashing and wall flashing are properly installed
FBC-R R903.2 - Roof penetration sealing
Verify all roof penetrations are properly sealed and flashed
FBC-R R903.2
Plumbing
Rough Plumbing
Conditional- Supply pipe sizing and materialCritical
Verify supply pipe sizes and material match approved plans
FBC-P 604.1 - DWV pipe sizing and slopeCritical
Verify drain, waste, and vent pipe sizes and slope per plans
FBC-P 704.1 - Pipe support and hangingCritical
Verify pipes are properly supported at required intervals
FBC-P 308.1 - Vent termination locations
Verify vent pipes terminate properly through roof
FBC-P 903.1 - Water heater rough-in
Verify water heater location, drain pan, and connections per plans
FBC-P 607.1
Electrical
Rough Electrical
Conditional- Panel installationCritical
Verify electrical panel is properly mounted and sized per plans
NEC 408.4 - Wire sizing per circuitsCritical
Verify wire gauge matches breaker amperage for each circuit
NEC 210.3NEC 240.4 - Box fill and installationCritical
Verify electrical boxes are properly installed and not overfilled
NEC 314.16 - GFCI and AFCI locationsCritical
Verify GFCI and AFCI protection is provided where required
NEC 210.8NEC 210.12 - Smoke and CO alarm wiringCritical
Verify interconnected smoke and CO alarm wiring is in place
FBC-R R314.3FBC-R R315 - Grounding and bondingCritical
Verify grounding electrode system and bonding connections
NEC 250.50
Mechanical
Rough Mechanical/HVAC
Conditional- Ductwork installationCritical
Verify duct sizes, routing, and support match approved plans
FBC-M 603.1 - Duct sealingCritical
Verify duct joints and connections are properly sealed
FBC-M 603.9 - Equipment placementCritical
Verify air handler and condenser locations per plans with required clearances
FBC-M 304.1 - Refrigerant line installation
Verify refrigerant line sizing and insulation per plans
FBC-M 1101.3 - Return air pathway
Verify return air pathways are properly sized and located
FBC-M 601.2
Building
Insulation
Conditional- Wall cavity insulation R-valueCritical
Verify wall insulation R-value matches energy calculations
FBC-E R402.1 - Ceiling/attic insulation R-valueCritical
Verify ceiling or attic insulation R-value per energy calculations
FBC-E R402.1 - Insulation coverage and gapsCritical
Verify no gaps, voids, or compression in insulation installation
FBC-E R402.4 - Air sealing
Verify air sealing at penetrations, top plates, and rim joists
FBC-E R402.4.1
Lathe, Siding
Conditional- Wall covering material and installationCritical
Verify exterior wall covering material matches approved plans and is properly installed
FBC-R R703.1 - Weather-resistive barrierCritical
Verify weather-resistive barrier is properly installed behind cladding
FBC-R R703.2 - Flashing at penetrations and transitionsCritical
Verify flashing is installed at windows, doors, and wall transitions
FBC-R R703.4 - Fastener pattern and spacing
Verify cladding fastener type and spacing per manufacturer and plans
FBC-R R703.1
Drywall
ConditionalBD-DependentMost jurisdictions skip this inspection for this project type. Confirm with your building department whether they'll require it.
- Drywall thickness and typeCritical
Verify drywall thickness matches plans, moisture-resistant board in wet areas
FBC-R R702.3.1 - Fastener spacingCritical
Verify screw or nail spacing meets code requirements
FBC-R R702.3.5 - Fire-rated assembliesCritical
Verify fire-rated walls and ceilings have proper drywall layers per rating
FBC-R R302.6 - Moisture barrier in wet areas
Verify moisture barrier behind tub/shower surrounds where required
FBC-R R702.4
Electrical
Final Electrical
RequiredTypical Final- Panel complete and labeledCritical
Verify panel cover installed, all breakers labeled, no open knockouts
NEC 408.4 - GFCI and AFCI operationalCritical
Verify all GFCI and AFCI devices test and reset properly
NEC 210.8NEC 210.12 - Receptacle and switch functionCritical
Verify outlets and switches operate correctly throughout
NEC 210.52 - Light fixtures installed
Verify all light fixtures are installed and operational
NEC 210.70 - Exterior lighting and outletsCritical
Verify exterior outlets are GFCI protected and lighting is functional
NEC 210.8NEC 210.52(E)
Plumbing
Final Plumbing
RequiredTypical Final- Fixture installation and operationCritical
Verify all plumbing fixtures are installed, connected, and operational
FBC-P 405.1 - Water heater installationCritical
Verify water heater is properly installed with TPR valve, drain pan, and discharge pipe
FBC-P 607.1 - No visible leaksCritical
Verify no leaks at any supply or drain connection
FBC-P 312.1 - Hose bibbs and exterior plumbing
Verify exterior hose bibbs have backflow prevention
FBC-P 608.15.4.2
Mechanical
Final Mechanical/HVAC
RequiredTypical Final- System operational testCritical
Verify HVAC system starts, runs, and produces heated and cooled air
FBC-M 304.1 - Air handler and condenser installationCritical
Verify equipment is properly installed with required clearances and level
FBC-M 304.1 - Condensate drainCritical
Verify condensate drain is properly routed and terminated
FBC-M 307.2 - Duct registers and grilles
Verify all supply and return registers are installed and operational
FBC-M 601.2 - Equipment labels and data plates
Verify equipment nameplates match approved plans for capacity and efficiency
FBC-M 304.1
Building
Final Building
RequiredTypical Final- Egress doors and hardwareCritical
Verify egress doors provide minimum 32-inch clear width and proper hardware
FBC-R R311.2 - Smoke alarms installed and operationalCritical
Verify smoke alarms in each bedroom, outside sleeping areas, and each level
FBC-R R314.3 - CO alarms installedCritical
Verify carbon monoxide alarms where required
FBC-R R315 - Emergency escape openingsCritical
Verify bedroom windows meet egress size requirements
FBC-R R310.1 - Stairway complianceCritical
Verify stair rise, run, handrail height, and landing dimensions
FBC-R R311.7 - Address numbers visible
Verify address numbers are posted and visible from street
FBC-R R319.1 - Exterior finishes complete
Verify exterior cladding, trim, and weatherproofing are complete
FBC-R R703.1 - Site grading and drainage
Verify finish grade slopes away from foundation minimum 6 inches in 10 feet
FBC-R R401.3