Multi Family

Multi Family Re-Pipe

Last updated: Apr 21, 2026

Section 1

Required Documents

Submit these with your initial project package.

Always required

  • Sealed Plumbing Plans

Section 2

Plan Review Criteria

What FCC's plans examiner looks for on this project type, by trade. Items are grouped by priority — life-safety first. Building department checks may go further; this is the FCC private provider scope under FL Statute 553.791.

PlumbingAdvisory

AdvisoryPlan review is not required for this scope under FBC 107.3.5. FCC reviews these items only when the building department specifically requires it, or when the client opts in.
  1. #01Re-pipe materials and scopeCode

    Re-pipe scope must show approved materials, routing, and fixture count consistent with DWV sizing.

    FBC-P 603FBC-P 709
  2. #02Plan review applicability (FBC 107.3.5)Documentation

    Per FBC-B 107.3.5, plan review is not required for minor plumbing repairs (Exemption #3). FCC performs this review only when the building department requires plan review or the client opts in.

    FBC-B 107.3.5

Items marked Advisory are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.

Section 3

Inspection Walkthrough

Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.

Plumbing

Phase #1

Final Plumbing

RequiredTypical Final
  1. Fixture operationCritical

    Verify all fixtures have proper hot and cold water flow with no leaks

    FBC-P 405.1
  2. No visible leaksCritical

    Verify no leaks at any new connection point under normal pressure

    FBC-P 312.1
  3. Wall and ceiling patches

    Verify access points are properly patched and finished

    FBC-B 110.3