- #01Re-pipe materials and scopeCode
Re-pipe scope must show approved materials, routing, and fixture count consistent with DWV sizing.
FBC-P 603FBC-P 709 - #02Plan review applicability (FBC 107.3.5)Documentation
Per FBC-B 107.3.5, plan review is not required for minor plumbing repairs (Exemption #3). FCC performs this review only when the building department requires plan review or the client opts in.
FBC-B 107.3.5
Multi Family Re-Pipe
Last updated: Apr 21, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Sealed Plumbing Plans
Section 2
Plan Review Criteria
What FCC's plans examiner looks for on this project type, by trade. Items are grouped by priority — life-safety first. Building department checks may go further; this is the FCC private provider scope under FL Statute 553.791.
PlumbingAdvisory
Items marked Advisory are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Plumbing
Final Plumbing
RequiredTypical Final- Fixture operationCritical
Verify all fixtures have proper hot and cold water flow with no leaks
FBC-P 405.1 - No visible leaksCritical
Verify no leaks at any new connection point under normal pressure
FBC-P 312.1 - Wall and ceiling patches
Verify access points are properly patched and finished
FBC-B 110.3