- #01Design wind speed & exposureLife Safety
Verify design wind speed (Vult) and exposure category match jurisdiction requirements for the project location.
FBC-B 1609FBC-B 2002ASCE 7-22 - #02Attachment to existing structureLife Safety
Verify connection details between the aluminum structure and the existing residence are shown with adequate fastener specifications.
FBC-B 2002.5FBC-R R301.1 - #03Footing design (if new footing)Life Safety
If scope includes new footings, verify footing dimensions, reinforcement, and depth are shown.
FBC-R R403FBC-B 1809 - #04Florida product approvalsCode
Verify Florida product approvals (FL#) or Miami-Dade NOA numbers are listed for fenestration, screen systems, or structural panels subject to wind load.
FBC-B 1708FBC-R R301.2.1.2 - #05Egress from enclosed areaCode
If the aluminum structure encloses an egress path from a sleeping room or dwelling unit, verify egress is maintained.
FBC-R R310FBC-R R311 - #06Engineer of record seal on structuralDocumentation
Confirm structural drawings bear a current Florida-licensed engineer's seal and signature.
Florida Statutes Chapter 471FBC-B 107.3.5
Single Family Aluminum
Screen enclosures, pool cages, carports, aluminum pergolas on existing footings
Last updated: Apr 20, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Construction Plans Sealed by a Florida Registered Design ProfessionalConstruction plans sealed by a Florida-registered design professional showing aluminum structure layout and framing.
- Site Plan / SurveySite plan or survey showing property boundaries, setbacks, and structure footprint.
Section 2
Plan Review Criteria
What FCC's plans examiner looks for on this project type, by trade. Items are grouped by priority — life-safety first. Building department checks may go further; this is the FCC private provider scope under FL Statute 553.791.
BuildingRequired
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Building
Final Building
RequiredTypical Final- Base rail attachment and tapcon spacingCritical
Verify base rail is secured with tapcons at correct spacing per plans
FBC-B 2002.1FBC-B 2002.4 - Post to base connectionCritical
Verify structural connection of posts to base rail
FBC-B 2002.1 - Post to roof beam connectionCritical
Verify structural connection of posts to roof beams
FBC-B 2002.1 - Gusset connectionsCritical
Verify gusset plates are installed at structural joints per plans
FBC-B 2002.1FBC-B 2002.4 - Beam to gutter connectionCritical
Verify beams are properly connected to gutter system
FBC-B 2002.1 - Gutter clips
Verify gutter clips are installed at proper intervals
FBC-B 2002.1 - Overall structureCritical
Verify overall shape and construction matches approved plans
FBC-B 2002.4 - Screen door opening mechanism height
Verify door latch/opening mechanism is at 54 inch height where pool barrier applies
NEC 680.26FBC-R R303 - Pool equipment bonding
If pool equipment is present, verify bonding wire at pool equipment and at structure
NEC 680.26 - Elite roof panel sealing
If elite (solid) roof panels are present, verify sealing is complete
FBC-B 2002.5