- #01Pool barrier compliance (if fence serves as pool barrier)Life Safety
If the fence encloses a swimming pool or serves as the required pool barrier, it must comply with ISPSC / FBC-R pool barrier requirements: minimum height, opening limits, latch height, and gate direction.
FBC-R R4501.17ISPSC 305 - #02Plan review applicability (FBC 107.3.5)Documentation
Fences are not listed in FBC-B 107.3.5 minimum plan review criteria for one- and two-family dwellings. FCC performs this review only when the building department requires plan review (commonly for pool-enclosing fences or tall fence wind loads) or the client opts in.
FBC-B 107.3.5 - #03Wind load for tall or solid fencesPerformance
Tall (over 6 feet) or solid fences in high-wind zones require engineered design or manufacturer product approval.
FBC-B 1609ASCE 7
Single Family Fence
Gates
Last updated: Apr 20, 2026
Section 1
Required Documents
Submit these with your initial project package.
Always required
- Site PlanSite plan showing fence location, height, and relationship to property boundaries
- Product SpecificationsProduct specifications for fence materials and design
Section 2
Plan Review Criteria
What FCC's plans examiner looks for on this project type, by trade. Items are grouped by priority — life-safety first. Building department checks may go further; this is the FCC private provider scope under FL Statute 553.791.
BuildingAdvisory
Items marked Advisory are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.
Section 3
Inspection Walkthrough
Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.
Building
Final Building
RequiredTypical Final- Post installation and depthCritical
Verify fence posts are set at proper depth and spacing per approved plans
FBC-R R301.1 - Fence height and setbackCritical
Verify fence height and setback from property line per approved plans
FBC-R R301.1 - Material and constructionCritical
Verify fence material and construction method match approved plans
FBC-R R301.1 - Gate operation
Verify gates open, close, and latch properly
FBC-R R301.1