Single Family Retaining Wall

Last updated: Apr 20, 2026

Section 1

Required Documents

Submit these with your initial project package.

Always required

  • Plans or Detailed Drawings
    Construction drawings showing retaining wall layout, dimensions, reinforcement, and drainage details
  • Site Plan / Survey
    Site plan or survey showing property boundaries, elevations, and retaining wall location

Conditional

  • Construction Plans Sealed by a Florida Registered Design Professional
    Construction plans sealed by a Florida-registered design professional when retaining wall exceeds 4 feet in height.
    WhenRequired if retaining wall exceeds 4 feet in height.

Section 2

Plan Review Criteria

What FCC's plans examiner looks for on this project type, by trade. Items are grouped by priority — life-safety first. Building department checks may go further; this is the FCC private provider scope under FL Statute 553.791.

BuildingAdvisory

AdvisoryPlan review is not required for this scope under FBC 107.3.5. FCC reviews these items only when the building department specifically requires it, or when the client opts in.
  1. #01Wall height, surcharge, and geotechnical assumptionsLife Safety

    Retaining wall design must address wall height, soil type, surcharge load (traffic/structure), and drainage.

    FBC-B 1807.2FBC-R R404
  2. #02Footing / foundation designLife Safety

    Footing or foundation design must show dimensions, reinforcement, depth, and connection to the structure above.

    FBC-R R403FBC-B 1809
  3. #03Plan review applicability (FBC 107.3.5 minimum criteria)Documentation

    Standalone retaining wall is not in FBC-B 107.3.5 minimum criteria for 1&2 family. FCC performs this review only when the building department requires plan review or the client opts in.

    FBC-B 107.3.5
  4. #04Engineer of record sealDocumentation

    Structural drawings must bear a current Florida-licensed engineer's seal and signature.

    Florida Statutes Chapter 471FBC-B 107.3.5

Items marked Advisory are non-blocking. Per FBC 107.3.5, plan review isn't required for these scopes — FCC reviews them when the building department requests it or the client wants the extra set of eyes.

Section 3

Inspection Walkthrough

Inspections are listed in their typical phase order. Your FCC inspector will confirm which apply to your project. Call (772) 222-6679 with questions.

Building

Phase #1

Footing, Slab, UFER

Required
  1. Footing dimensionsCritical

    Verify footing width and depth match approved plans

    FBC-R R403.1FBC-R R403.1.1
  2. Rebar size and spacingCritical

    Verify rebar size, spacing, and placement per plans

    FBC-R R403.1
  3. UFER grounding electrodeCritical

    Verify minimum 20 feet of #4 bare copper or rebar is encased in footing

    NEC 250.52(A)(3)
  4. Slab vapor barrierCritical

    Verify vapor barrier is installed under slab per plans

    FBC-R R506.2.3
  5. Slab thickness and wire meshCritical

    Verify slab thickness and reinforcement per plans

    FBC-R R506.1
  6. Foundation anchorage layout

    Verify anchor bolt placement for sill plate attachment

    FBC-R R403.1.6
Phase #2

Final Building

RequiredTypical Final
  1. Egress doors and hardwareCritical

    Verify egress doors provide minimum 32-inch clear width and proper hardware

    FBC-R R311.2
  2. Smoke alarms installed and operationalCritical

    Verify smoke alarms in each bedroom, outside sleeping areas, and each level

    FBC-R R314.3
  3. CO alarms installedCritical

    Verify carbon monoxide alarms where required

    FBC-R R315
  4. Emergency escape openingsCritical

    Verify bedroom windows meet egress size requirements

    FBC-R R310.1
  5. Stairway complianceCritical

    Verify stair rise, run, handrail height, and landing dimensions

    FBC-R R311.7
  6. Address numbers visible

    Verify address numbers are posted and visible from street

    FBC-R R319.1
  7. Exterior finishes complete

    Verify exterior cladding, trim, and weatherproofing are complete

    FBC-R R703.1
  8. Site grading and drainage

    Verify finish grade slopes away from foundation minimum 6 inches in 10 feet

    FBC-R R401.3